
Sanjaykumar Mistry
Sr. Electrical Engineer

Connect with Sanjaykumar Mistry to Send Message
Connect
Connect with Sanjaykumar Mistry to Send Message
ConnectTimeline
About me
Project Manger at Solarplus Energy Solutions
Education

The Maharaja Sayajirao University of Baroda, Polytechnic -Faculty of Engg & Technology.
1978 - 1981Engineer’s Degree Electrical, Electronics and Communications Engineering APassed Three years diploma course with First class in Electrical Eng- from M.S. University of Baroda in July 1981.Passed Degree in Electrical engg with second class from M.S. University of Baroda in November 2004..

Shri Sarvajanik Highschool, Waghodia,Vadodara
1975 - 1978Secondary School certificate Science
The Maharaja Sayajirao University of Baroda
1999 - 2004Bachelor's degree in Electrical engineering Electrical, Electronics and Communications Engineering Second
Experience

Haldyn Glass Gujarat Limited
Jul 1996 - Aug 1997Sr. Electrical EngineerWorked as Sr.Electrical engineer and responsible for construction,commissioning of Electrical equipment.Modified preventive maintenance schedule of slip ring induction motors and reduced breakdown and cost of carbon brushes.Operation and maintenance of Power generation plant without any failure.Trouble shooting of electrical system of IS machines.UPS system -Illumination system,Liasioning with Electrical Inspectors and DISCOM authorities.Manpower selection and their training as per required schedule.Approval of construction work done by contractors and their billing approval. Show less

ViniRoyal Plasticoates-Unit of SAMSON-India
Sept 1997 - Mar 2006Assistant ManagerAt ViniRoyal Plasticoates-Unit of SAMSON-India,I was involved for following roles and responsibilities.Extensive experience in the field of Consultancy , Project Management, Design Management, Project Engineering, Electrical & Electronics Engineering, Instrumentation, Control Engineering, Industrial Automation Engineering, Design Engineering, Site Management, Factory Acceptance Testing, Site Acceptance Testing, Client Interface Management, Pre-Commissioning/Commissioning, Shutdown Management, Schedule Management, Maintenance Engineering/Management and Resource Management.Some of Key tasks: • To form and manage the Commissioning Team in all phases of site execution.• Provide Technical inputs, method statements, Pre-commissioning and Commissioning activities according to the plant operations methodology.• To prepare planned site execution schedules and liaise with End User for smooth implementation.• Managed the Design Engineering, Project Execution of Industrial Control System and field instrument standardization, using standards IEEE, IS indian standard.• To manage all phases of the projects, including design analysis and finalization.• Involvement in preparation, issue and implementation of detailed Engineering packages / documents, work packs, drawings, calculation.Installation and commissioning of continues plant and then operation and maintenance of Utilities equipment like, Thermic fluid Oil heaters,Air compressors, Power generation plant, Chilling water plant.Electrical substation.Manpower selection.Contractor-subcontractor selection and approval of billing.local purchase of engineering materials.Liasioning with government agencies. Show less

Hyundai Heavy Industries Co., Ltd.
Jan 2006 - Jan 2008Electrical EngineerConstruction Engineer for Electrical and cathodic protection system in crude export facilities expansion project of Kuwait oil company. North and south tank farm electrical system for substations,control rooms. All cable installation ,supervision.pre-commissioning, Co-ordination between client and contractors of other desciplines.Day to day planning and execution,submission of progress reports ,Monitoring /inspection of electrical work with quality and safety standards of KOC.Active Participation in clients meetings related to Project issues. Show less

Dodsal E & C Pte Ltd
Jan 2008 - Jan 2010ManagerOverall incharge of Electrical construction project of train 6,7 of RAS GAS/CTJV and and AKG/CTJV units. GASCO/Abudhabi for sulfur project expansion.Extensive experience in the field of Consultancy , Project Management, Design Management, Project Engineering, Electrical & Electronics Engineering, Instrumentation, Control Engineering, Industrial Automation Engineering, Design Engineering, Site Management, Factory Acceptance Testing, Site Acceptance Testing, Client Interface Management, Pre-Commissioning/Commissioning, Shutdown Management, Schedule Management, Maintenance Engineering/Management and Resource Management.Some of Key tasks: • To form and manage the Commissioning Team in all phases of site execution.• Provide Technical inputs, method statements for Hot Cut-Over to the definition of the SAT, Pre-commissioning and Commissioning activities according to the plant operations methodology.• To prepare planned site execution schedules and liaise with End User for smooth implementation.• Managed the Design Engineering, Project Execution of Industrial Control System and field instrument standardization, using standards IEEE, ANSI, SHELL, • To manage all phases of the projects, including design analysis and finalization.• Issue detailed project scheduled up to L4 in . Involvement in preparation, issue andimplementation of detailed Engineering packages / documents, work packs, drawings, calculation . Show less
%20LTD..webp)
AMEC FOSTER WHEELER (GB) LTD.
Sept 2010 - Mar 2015Sr.Principal Engineer,PDRP-IOCL Refinery.I have joined Foster Wheeler- in Sept-2010 ,for their contract with Indian Oil Corporation ( IOCL)-Paradip Refinery Project,Orissa,India.Involved in construction of EHV/HT GIS electrical Distribution substation and other 15 nos substation in grass route refinery, Involved from site leveling to the commissioning stage of Electrical systems and resolved all complicated interface issues of all consultants of different units of the project. I was engaged for Managing the PMCs role( MPMC) ,on behalf of the client. All the technical issues encountered during the construction face were successfully solved and full satisfaction of the client as per the project specification. Planned cable laying schedule in common UG trenches for all contractors/consultants of the project and implemented successfully,with quality and safety.Involved in Field engineering and Relocated the High mast lighting towers all over the project as per the requirement of the project units of different contractors.Temporary construction power and emergency power feeders to the project were successfully reinstated.Monitored the progress of two consultants EPCM-2 and EPCM-7 of PDRP project.Responsible for forecast of the completion date of the substations to the client as per the ongoing construction progress.Active participation in the weekly and monthly meetings with contractors and clients as part of the project activity to access the real progress and helping them to solve the issues.Provided expert advice/recommendation to client and consultant for technical issue.Monitored the daily manpower at site for EPCM-2 and EPCM-7 Electrical substation Package. Show less

GS Engg and Construction,
Apr 2015 - May 2017General ManagerSome of Key tasks: • To form and manage the Commissioning Team in all phases of site execution.• Provide Technical inputs, method statements , Pre-commissioning and Commissioning activities according to the plant operations methodology.• To prepare planned site execution schedules and liaise with End User for smooth implementation.• Implementation of detailed Engineering packages / documents, work packs, drawings, calculation .Responsible for E & I construction work in brown field of Mina Al Ahmadi Refinery,Kuwait. This project has many challenges before actual start of construction Like searching, relocating/removal of underground live utilities through the plant. As a main contractor all UG facilities were studied and relocated to finalise the HV and LV cable routes.Successfully Shifting of live communication cables Fiber optic and others with Manhole were with high care. This was important to design Hv cable route within the complex UG utilities.Transportation , erection and assembling of Packaged substations in running refinery was a big challenge,it was successfully completed at site. There Four substations for GSEC scope.Coordination with transport contractor and vendor was done successfully for all substations and Emergency DG Sets in the project.Actively Involved in shutdown work of Unit 25 for two times to complete the additional electrical starters, MCCs for Flare and later for unit 25 within time limit.Coordinated with CP system vendor and execution contractor to complete execution of Cathodic system for Tanks 4 nos and UG pipe lines/ Road crossings of the project.Precommissioning of the Electrical Motors with associated electrical gears were done in the project. Also resolved the teething issues instantly.Coordinated with Process Operation team,client construction/maintenance team and contractors to minimize the unsafe work practice, Timely delivery of the construction work and avoiding rework/rejection. Show less

Petrofac international, UAE
May 2017 - Oct 2018Dy.MangerExtensive experience in the field of Consultancy , Project Management, Design Management, Project Engineering, Electrical & Electronics Engineering, Instrumentation, Control Engineering, Industrial Automation Engineering, Design Engineering, Site Management, Factory Acceptance Testing, Site Acceptance Testing, Client Interface Management, Pre-Commissioning/Commissioning, Shutdown Management, Schedule Management, Maintenance Engineering/Management and Resource Management.Some of Key tasks: • To form and manage the Commissioning Team in all phases of site execution.• Provide Technical inputs, method statements for Hot Cut-Over to the definition of the SAT, Pre-commissioning and Commissioning activities according to the plant operations methodology.• To prepare planned site execution schedules and liaise with End User for smooth implementation.• Managed the Design Engineering, Project Execution of Industrial Control System and field instrument standardization, using standards IEEE, ANSI, SHELL, • To manage all phases of the projects, including design analysis and finalization.• Issue detailed project scheduled up to L4 in . Involvement in preparation, issue andimplementation of detailed Engineering packages / documents, work packs, drawings, calculation .Engaged for E & I construction work of AL Taweela Alumna ATA / Refinery at KIZAD-Abudhabi.Client Emirates Global Aluminium ( EGA )in UAE.This project estimated cost is about 3 bn USD.Responsible for day to day monitoring and supervision of contractors' progress as per project specification ,quality and safety regulation of the project.Responsible for solving field Engg issues during construction stage , suggesting acceptable solution within the company's design criteria.Monitoring of manpower V/s Progress per day /weekly/monthly basis.Helping contractor for Progress planned V/s Progress achieved. Show less

Petrofac Saudi Arabia
Oct 2018 - Jun 2019Dy.MangerExtensive experience in the field of Consultancy , Project Management, Design Management, Project Engineering, Electrical & Electronics Engineering, Instrumentation, Control Engineering, Industrial Automation Engineering, Design Engineering, Site Management, Factory Acceptance Testing, Site Acceptance Testing, Client Interface Management, Pre-Commissioning/Commissioning, Shutdown Management, Schedule Management, Maintenance Engineering/Management and Resource Management.Some of Key tasks: • To form and manage the Commissioning Team in all phases of site execution.• Provide Technical inputs, method statements for Hot Cut-Over to the definition of the SAT, Pre-commissioning and Commissioning activities according to the plant operations methodology.• To prepare planned site execution schedules and liaise with End User for smooth implementation.• Managed the Design Engineering, Project Execution of Industrial Control System and field instrument standardization, using standards IEEE, ANSI, SHELL, • To manage all phases of the projects, including design analysis and finalization.• Issue detailed project scheduled up to L4 . Involvement in preparation, issue andimplementation of detailed Engineering packages / documents, work packs, drawings, calculation .completed Construction of Electrical and instrumentation system in KOD, FLARE and Sulphur loading arms ,storage tanks. Emergency generator , Substation. Show less

Solarplus Energy Solutions
Aug 2019 - nowProject MangerEngineering ,Procurement and construction of Solar energy projects.Consultant for Energy saving.
Licenses & Certifications

QMS 9001-2008
TUV-NORD
Languages
- enEnglish, hindi, gujarati
Recommendations

Rahul mane
IIFT Delhi | Jio Platforms | Sattva | IIESTDelhi, India
Simon rathje
Director Sales & Logistics bei Rokaflex GmbHGreater Hamburg Area
Jessica lai
Seemarket Technology Co.,Ltd. - Sales ManagerGuangdong, China
Sivaprasad gundapaneni
Data Engineer-Bigdata-Hadoop।Spark-Scala।Pyspark।AWS|Java।Shell scripting।GIT|JENKINS।Python।Sonar।O...Venkatagiri, Andhra Pradesh, India
Ashish jadhao
Chief of Staff, B2B Product | FMS Delhi | IIT BombayMumbai, Maharashtra, India
Juan francisco bermejo manso
Arquitecto y Administrador de Fincas - Socio en IAMP Administración de Fincas - Certificado de Espec...Greater Madrid Metropolitan Area
Claudio sepúlveda schutz
Líder UX UI en Caja Los AndesSantiago, Santiago Metropolitan Region, Chile
Sheikh daniyal ahmed
Account Manager - Amazon Shipping | Ex-Careem (Uber Division) | Client Servicing & Data AnalysisHayes, England, United Kingdom
Madhankumar a snsacd
Mathematics Teacher at SNS ACADEMYCoimbatore, Tamil Nadu, India
Skyler vondeben
Systems Engineer at Booz Allen Hamilton, NASA Johnson Space CenterHouston, Texas, United States
Md. saiful islam
Head of Network & Database Infrastructure (Sr. Manager) at BSRM Group of Companies, MTCNA | RHCSA | ...Chattogram, Bangladesh
王昌众
Structure EngineerJing'an District, Shanghai, China
Maaike van bergen
Operationeel Medewerker bij Gateway Cargo Systems GmbHRotterdam, South Holland, Netherlands
Aditya pandu wicaksono
Manager Well & Project Service Procurement at PT Medco E&P Indonesia | MSc Industrial and Systems En...Indonesia
Danielle rudolph
Product | Strategic Leader | Innovator | B2C & B2BWestern Springs, Illinois, United States
Reece richardson
Product Owner | Client AdvocateBrisbane, Queensland, Australia
Diana fernández méndez
Profesora Ayudante Doctora en Universidade de Santiago de CompostelaLugo, Galicia, Spain
Sreemoyee sarkar
Project Manager at CiscoBengaluru, Karnataka, India
Katri kilpiä
Production Manager at Ilosaarirock FestivalJoensuu, North Karelia, Finland
Mobolaji olanrewaju
Manager/Senior Business Travel Consultant, CAC Consultant, Writer and AuthorLagos State, Nigeria
...