
Glen Carter
Project Engineer

Connect with Glen Carter to Send Message
Connect
Connect with Glen Carter to Send Message
ConnectTimeline
About me
Highly Skilled Project and Construction Manager/Engineer
Education

San Fernando Technical Institute, Trinidad
1984 - 1987Technician Diploma Construction Engineering
The University of the West Indies
1988 - 1991Bachelor's degree Mechanical Engineering
Experience

Damus Limited
Jan 1991 - Jan 1995Project EngineerExecuted multiple construction projects within the petroleum and petrochemical industries. Projects including fabrication and installation of process plant piping, pipelines and structural steelwork, fabrication and erection of water, oil and diesel storage tanks, mechanical equipment repairs/installation, concrete foundations, EI&C works and blasting & painting.

SNC Lavelin Trinidad Limited
Jan 1995 - Jan 1997Field Piping EngineerPetrotrin Point-a-Pierre Refinery Upgrade Project:Played integral role in project planning and execution for unit upgrades and construction of a new grassroots plant from spool fabrication to erection phase. Some responsibilities included revision of piping isometric drawings, compilation of steam tracing nomenclature and schedules, development of hydrotest packages and post hydrotest verification of system mechanical completion.

Amoco Trinidad Oil Company
Jan 1997 - Jan 2000Project EngineerEngineering & Construction: Liaised with Facilities Engineers and Upsteam Development Team Engineers to plan, manage and execute several on-shore and off-shore projects for Amoco’s Oil Asset and Terminal Operations. Prepared scope of work, project schedule and cost estimates, monitored and reported on project performance, and provided quality assurance for projects such as Teak field sea flare tripod repair, Teak E platform vent boom installation, Galeota Point Terminal flare upgrade, Teak-AP platform to Teak-B platform 8-inch subsea coflexip pipeline installation and Cassia platform to Teak-AP platform 8-inch subsea condensate pipeline and riser repair. Show less

BP Amoco Energy Company of Trinidad & Tobago
Jan 2000 - Jan 2003Project EngineerKapok Project:Project Engineer on client Project Management Team responsible for design and installation of two major offshore platforms for Trinidad. Total Facilities Cost US $270 million.- Conducted feasibility study, and convinced Senior Management to build major components in Trinidad.- Developed construction plan and recruited key employees to work at the construction site.- Identified and managed risk associated with fabrication, assembly and load-out of platform components.- Interfaced with Engineering and Fabrication Contractors to provide constructability input during design and resolve EPC issues in the field. - Reviewed and approved Fabrication Contractor safety and work execution plans to provide assurance that platform components were fabricated in accordance with approved ICF drawings, codes, standards and project specifications.- Proactively managed safety of all project personnel including Contractors in the fabrication yard and delivered quality components on schedule and within budget. Show less

BP Trinidad and Tobago LLC
Jan 2003 - Jan 2007Project ManagerNew Oil Export Loading (NOEL) Pipeline Project: Successfully managed design and installation of a new 30-inch pipeline, Pipeline End Manifold and Single Point Mooring system. The selected route included a revamp onshore portion, a complex HDD shore approach and offshore pipelay. Total Facilities Cost US $80 million. - Evaluated and awarded EPC contracts and monitored Contractor performance to ensure compliance with BP’s quality and safety standards.- Recruited, coached and supervised core team of 15 technical and professional staff; led team in developing project execution plan and risk management plan, and coordinated project assurance activities such as HAZOP, BRISK and ALERT to effectively manage risk throughout the project.- Developed and implemented Action Tracking Matrix and conducted cost, schedule, safety and technical reviews to ensure timely achievement of project deliverables. - Prepared reports and facilitated review meetings to inform Project Team and Senior Management of project status; submitted Financial Memorandum and Authorization for Expenditure to Senior Management to secure approval and funding for each phase of the project.- Overcame challenge of managing complex interfaces; was innovative taking advantage of delay to change and optimize pipeline route. - Liaised with BP’s Health, Safety and Environment (HSE) Department and the Environmental Management Authority (EMA) to conduct Environmental Impact & Social Assessment; obtained Certificate of Environmental Clearance and proactively managed HSE performance throughout the project to ensure that all project activities were executed in accordance with BP and local regulatory standards.- Maintained good communications with external stakeholders including representatives from the Ministry of Energy and community-based non-governmental organizations to provide timely project updates and solicit feedback. Show less

Carillion (Caribbean) Limited
Jan 2007 - Jan 2012Project EngineerPROJECT: BPTT TERMINAL FIREWATER PUMP RELOCATION PROJECT • Provided ready and reliable technical support during the development of work procedures and lift plans for civil, piping and structural works.PROJECT: EOG KISKADEE PLATFORM STRUCTURAL REPAIRS AND REFURBISHMENT PROJECT • Successfully managed and led the fabrication and installation of new/replacement piping and structural steel, including scaffolding, lifting & rigging and painting work.PROJECT: NMWG/BPTT IMMORTELLE PLATFORM HELIDECK UPGRADE PROJECT • Developed efficient lift plans and procedures for the lifting and handling of helideck components (pipe trusses and structural frames/modules ranging from 7 to 22 Ton) in the Fabrication Yard.• Coordinated mock-up fit-up procedure for assembly of helideck components in the Fabrication Yard to verify fit-up before load out and shipping of helideck components offshore.PROJECT: DYNAMIC/BHP BILLITON ANGOSTURA GAS PROJECT • Successfully managed and led shop the fabrication and supply of resources (including labour, materials and equipment) for offshore construction and commissioning support works. PROJECT: NGC TOBAGO GAS RECEIVING AND METERING FACILITY PROJECT • Successfully managed and led the fabrication and installation of underground piping systems, structural steel pipe racks and perimeter fencing works.PROJECT: PETROTRIN NHT & CCR PLATFORMER COMPLEX PROJECT • Generated comprehensive method statements for civil and piping works.• Planned and coordinated major temporary works for the design and installation of formwork support systems for suspended and elevated concrete slabs. • Identified test packages, test pressures and test limits/boundaries for utility and process piping systems. PROJECT: PPGPL PHASE III GAS PLANT EXPANSION PROJECT • Successfully managed and led the delivery of civil and road works. Show less

WorleyParsons Trinidad Limited
Jan 2012 - nowConstruction Interface Manager/Project ManagerPROJECT: ATLANTIC ENGINEERING MSA PORTFOLIO • Effectively led/managed constructability input during engineering design, provided construction and procurement support and interface coordination with Customer, construction Contractors and Engineering during the selection, design and execution of multiple onshore brownfield engineering projects through Select, Define and Execute Phases some of which were driven by Turnarounds / Shutdowns.• Successfully led/facilitated planning and preparation works for Project Constructability Reviews. • Key participant in 3D Model / Design Reviews, Risk and Opportunity Reviews and Customer Value Assurance Reviews. • key projects included:o Train 1 and Common Facilities Life Extension. o Effluent Management Sewage Treatment Package (STP) Upgrade Trains 1 & 4.o Cold Temperature Metal Embrittlement (CTME) Train 4 Packages 1 & 3 Piping CS-SS Change Out. o Train 4 Regeneration Gas Circuit Upgrade.o NGL Stabilization for All Trains o Instrument Air Upgrade All Trains.PROJECT: MULTI-CUSTOMER MISCELLANEOUS PROJECTS PORTFOLIO • Effectively managed a project team of 12 people while spearheading the delivery of multiple miscellaneous brownfield engineering projects (onshore and offshore). • Successfully led the selection definition and execution of projects stages while ensuring timely completion, within the set budgets. • Established close working relationships with Customers, including BPTT, BGTT, BHP Billiton, Repsol and NGC.• Key projects included:o BHP Billiton Crude Oil Transfer Pumps Replacement CPP Platform.o BGTT Instrument Air and Nitrogen Upgrade Dolphin Platform / Beachfield.o BGTT Mahogany B Platform Hub Bypass.o NGC Third Emergency Bypass and Condensate Tank. Show less
Licenses & Certifications

Registered Engineer
Board of Engineers of Trinidad and TobagoJan 2003
API-510 Pressure Vessel Inspector Certification Program
API - American Petroleum InstituteJan 2000
API-570 Piping Inspector Certification Program
API - American Petroleum InstituteJan 1998
Project Management Professional
Project Management InstituteJan 2003
API-653 Tank Inspector Certification Program
API - American Petroleum InstituteJan 1999
Recommendations

James dentith
Matching talent with opportunity, helping businesses grow through apprenticeshipsSelby, England, United Kingdom
Anindita neogi
Consultant at Deloitte ConsultingHyderabad, Telangana, India
Mike lamb
Owner/Producer at On The Money ProductionsCitrus Heights, California, United States
Ana van bilsen irías
Impact Manager at Better Society Capital | Associate at Women in Social Finance | Co-Founder of Futu...London, England, United Kingdom
Antonette rodriguez
Assistent og omsorgspleierSkien, Vestfold og Telemark, Norway
Tirenioluwa adenuga
Grad Student of Information Security Management | Governance, Risk and Compliance (GRC) | Cybersecur...SAPPHIRE VIRTUAL NETWORKS LIMITED
Eli quay
Communications & Media Relations Specialist at Bridgewater CollegeGreater Charlottesville Area
Nitisha agarwal
Manager- WTS Dhruva | Ex-PwC| Ex- KPMGMuscat, Masqaţ, Oman
Diana figueredo
Agente de viagens e supervisora de vendas na HT Moto TurismoFoz do Iguaçu, Paraná, Brazil
Rosta sara
Open to WorkSan Prospero, Emilia-Romagna, Italy
Maroš milčik
10x Certified Salesforce Consultant - ContractorSlovakia
Jessica chiroque rosales
Coordinador de Solución de Relacionamiento CRM y uPlanner | AWS Connect ® | SALESFORCE © | M3.0 © | ...Peru
Joshua laurence
Chief Growth Officer at Accessible Home Health CareMiami, Florida, United States
Ania smith
Production Lead for Publishing Platform at JagexGreater Norwich Area, United Kingdom
Sami essid
Business Advisor | Economic development officer | EntrepreneurOttawa, Ontario, Canada
Barkath ali mohamed iqbal
Lead Resident Engineer @ SITSingapore
Paul bryan
President at Prime Construction & RemodelingWest Chester, Pennsylvania, United States
Corinne bourbeillon
Journaliste à Ouest-FranceGreater Rennes Metropolitan Area
Alessandro carvalho
Lead Tech Support Engineer IIISão Paulo, São Paulo, Brazil
Bhavesh kumar tomer
Product Manager @Cvent | IIM K - MBA | Design Thinking Practitioner | ISB - Product ManagementGurgaon, Haryana, India
...