Sampath Kumara

Sampath kumara

bookmark on deepenrich
location of Sampath KumaraColombo, Western Province, Sri Lanka
Followers of Sampath Kumara103 followers
  • Timeline

  • About me

    Engineering Manager, MSc (CPM), BSc (Civil & Str) 1st Class, Eng (Dip), GMICE-UK,MIIESL

  • Education

    • Birmingham city university

      2019 - 2021
      Msc construction project manager upper 2 nd class
    • Institute of engineering technology (iet), katunayake, sri lanka

      1996 - 2000
      National diploma in engineering sciences civil engineering
    • Liverpool john moores university

      2013 - 2014
      Bsc civil & structural civil engineering 1st class
  • Experience

    • Sierra construction (pvt) ltd

      Apr 2001 - Nov 2003
      Assistant site engineers

      This is 15 story Apartment Building including 250 apartments.Duties Pilling Works (600 Dia. 104 No’s) Structural Works Including Steel Form Works, Reinforcements (Scheduling, Placing) Surveying & Levelling Works Preparation of Quantity, Take Off-Site Measurements

    • Wakachiku construction co ltd

      Nov 2003 - May 2005
      Assistant engineer.

      Construction of New Port; New Quay Wall (200m); Main break water (North and South); Revetments and Warehouses. Project Value USD 65 million. Duties Dredging the Harbor Basin Using Dredger Reclamation of Land Using Dredge Materials by Spreading Earth in Layers and Compacted To The Design Strength. Sheet Pile Driving Capping Concrete for Quay Wall Construction Main Break Waters (North and South) And Revetments (Laying Geo Fabric) Eco Sounding to Ascertain the Dredging Volume in the Harbor Basin. Reclamation and Steel Erection for Warehouse. Surveying & Levelling works. Show less

    • Kumagai gumi co., ltd.

      Sept 2005 - Jan 2012
      Bridge engineer

      Southern Transport Development Project, 24,000 Million funded by ADB - First highway project in Sri Lanka. The project consists of 60km length 4 lane highway; 22 road and river bridges, 89 metal underpasses and around 100 box culverts and pipe culverts; Bridges - Pilling (Bored, Pre-Cast), Cofferdams Waler systems.

    • Ksj - dce joint venture

      Feb 2012 - Jul 2013
      Construction manager

      Southern Transport Development Project (South section (Galle – Matara) 18,000 Mln.funded by Exim Bank CHINA Total project cost 20,000 million Sri Lanka rupeesThe project consists of 30km length 4 lane highway, 15 No’s road and river bridges, 40 metal underpasses; 100 box culverts and pipe culverts.Duties Handling all construction work (Earthwork & Structural work) Post Tensioning Pose Cooling Systems –RCBU (Decks, and Walls) Metal Arch- Shape control, Backfilling Soft Ground Treatment Construction of RCBU /RCBC /RCP (900 – 1500mm) Daily site meeting handling and work schedule Participating in Monthly progress meeting with consultant and client, behalf of the company Monthly/weekly/daily work programmed and progress monitoring Show less

    • Roughton international. (uk inter. eng. consultants company)

      Jul 2013 - May 2015
      Civil engineer

      World Bank Funded Road Sector Assistant Project – II - 3000 Million. Rehabilitation and Improvement of Galle road (A 002 & AB011) (Ratmalana to Panadura) Road Pavement overlaying and base correction (selected areas) Improvement of drainage paths Replace the new water distribution line  Improvement of footpaths and road finishersDuties Daily Supervision and approval of project activities Preparation of daily/weekly work programs. Design review and comment to the designer Preparation weekly/monthly progress reports Dedicate to HSE in the work environment Best effort to resolve construction issues Maintain construction quality as per project standards. Show less

    • Jacobs ( ch2m hill)

      Jul 2015 - Dec 2017
      Engineer (structure & tunnel)

      Qatar Expressway Program,Al Wakra Bypass Expressway project (Package -15),Project-015 Expressway Project within Group 1 of the Expressways Programme being executed on Design, Build & Construct basis, (Road length 12.00KM) in State of AL-Wakrah, Doha QatarTotal Project cost 3.2 Billion USDThe Project consists of 12 Km length 8 lanes carriageway,5 No’s of interchanges, 25 No’s of wire duct overhead bridges (Nearly 7Km of Wire Duct Bridge Length), One Major Tunnel,8 No’s of vehicular underpasses,24 No’s of Cyclist underpasses. Duties Handling of project structural activities at Bridges and Tunnel. Handling of PC girder Erection - Petroleum structures (with 600T Crane) Preparation of daily/weekly work programs. Design review and comment to the designer Preparation weekly/monthly progress reports Dedicate to HSE in the work environment Best effort to resolve structural issues Maintain construction quality as per project standards. Attend the construction-related short course and implement in best Show less

    • Corporation - japan

      May 2018 - now
      Engineering manger

      New Bridge Construction Project Over the Kelani RiverPackage -1: Steel Bridge Section.Total Project cost Rs 31.5 Billion • Construction of Main Line consisting of Steel Bridge Section (Package 1) & Extradosed Bridge Section (Package 2) parallel to the existing bridge connecting CKE and Base Line Road• Construction of Elevated Road towards the Port Access Road• Construction of Interchange and Junctions• Improvement of At-grade RoadDuties Review the design of temporary Structures – Coffer Dams, Earth Retaining Systems & Erection Systems. Handling of project structural activities at Bridges. Including Cofferdams, Pile Caps & relative superstructure. Handling of heavy machinery complying with modern safety standards.  Preparation of daily/weekly work programs. Design review and comment to the designer Preparation weekly/monthly progress reports Dedicate to HSE in the work environment Best effort to resolve structural issues Maintain construction quality as per project standards. Show less

    • Taisei corporation 大成建設株式会社

      Jun 2022 - now
      Manager - structural engineering & design

      BIA Terminal 2 Development Project (Phase II, Stage 2)To increase the capacity 15 million passengers per annum, Construction of a New Passenger Terminal Building (110,000m2), New Pier 2 (30 000m2) & Pier 3 (40,000m2) including an overhead access network, and other facilities under the Eco-Airport concept.