
Timeline
About me
Technical Engineer at JH Construction W.L.L
Education

Anna university chennai
2009 - 2013Bachelor's degree civil engineering frist class
Experience

Sri annamaar & co
Sept 2012 - Aug 2015Civil engineerWork objective Combined court building seven judicial magistrate courts will three floors of office. Road, MEP, pile foundation compound wall and bridge pier (four deck slab, two abutments and three pier foundation).Role & Responsibilities- Preparing the construction design of interior, elevation, wall panel, layout plan and parapet wall design.- Design calculation preparation and stability check for the three-pier foundation and four deck slab and abutment reinforcement for pier bridge.- Preparing BSS schedule for base slab, wall, bridges reinforcement.- Design calculation preparation for tapered pyramid roof with steel reinforcement.- Design preparation of MEP and electrical connection. Show less

Qd-sbg construction
Aug 2015 - Sept 2018Technical engineerWork objective As part of the expressway program. The Dukhan highway east project runs around 11.7km from the Bani hajer interchange (West) to the tilled interchange (East) and along Al Gharaffa Road from Al Rayyan Street (South) to Thani Bin hasim street (North).Role & Responsibilities- Review the IFC drawing of Section-5 Bani hajer Interchange (Roundabout, With Link1 and Link2 bridge, Camel bridge, Link 2 underpass, Rayyan underpass), Roads and wet & dry Utilities.- Preparing BSS schedule for base slab, wall, bridges reinforcement.- Posttensioning bridge stability calculation and load acting of the bridge calculation and design review and submitted to consultant to obtain approval.- Preparing the concrete pouring sequence for retaining wall and base slab casting as per QCS2014 Specification.- Review and submit the shop drawing on time before execution work at site and make sure of Xref file and layer are according the PWA CAD standard manual version 5.0.- RFI (Request for information) will be raised when encounter with utilities clashing. E.g. Manhole to manhole pipe connection will be clashed by another manhole. In that case we rise RIF and propose a proposal illustrate sketch showing by profile.- Review and submit red mark drawing to the consultant. The changes made at site during construction by RFI and other due to existing utilities and ducts.- Final Survey as-built Rev-Z by PWA CAD standard manual version 5.0. will be submit to the consultant for approval and handover inspection.- Traceability and tracking of work completion of each area road and utilities- GIS attributes and recorded as built submit to the end user for proper handing over. Show less

Jh construction w.l.l
Sept 2018 - nowDesign review technical engineerWork objective Road improvement works contains three package site instructions each has existing & proposed dry utilities and wet utilities. Existing Roads widening and newly proposed 8 lane road works then open cut and micro tunneling work.Role & Responsibilities- Review IFC drawing and make a report including any additional information or missing drawing form the consultant and make sure of QDRS approval from Kahramaa, QNBN…- We have encountered foul sewer coming under asphalt widening due to that need to do chamber lowering. So, the existing cover slab will be removed and replaced with new cover slab calculated to withstand the load and with steel reinforcement then taken approval from Consultant.- Prepare the BBS and checked the design requirements.- Existing portable air value chamber come under the asphalt, it should be lowered and extended to near island. Review design of existing chamber load then calculated the additional reinforcement of stability.- Reviewing the design calculation of precast manhole of 1800, 2100, 5100 Día manhole with depth of more than 31 meter submitted to consultant and taken approval.- Review and submit the shop drawing on time before execution work at site and make sure of Xref file and layer are according the PWA CAD standard manual version 5.0.- RFI (Request for information) will be raised when encounter with utilities clashing. E.g. Manhole to manhole pipe connection will be clashed by another manhole. In that case we rise RIF and propose a proposal illustrate sketch showing by profile.- Review and submit red mark drawing to the consultant. The changes made at site during construction by RFI and other due to existing utilities and ducts.- Final Survey as-built Rev-Z by PWA CAD standard manual version 5.0. will be submit to the consultant for approval and handover inspection.- Cut and fill quantity analysis and stockpile quantity analysis. Show less
Licenses & Certifications

Iso 9001:2015 - quality management system (internal auditor training ) ,diploma in computer application
Guardian independent certification limited, cscFeb 2016
Pmp
Chicago training centerNov 2016
Languages
- enEnglish
- hiHindi
- taTamil
- maMalayalam
Recommendations

Yi-sheng lin
Computer Hardware R&D Manager at PegatronYilan County, Taiwan, Taiwan
Riyad essebae'e
Mechanical Maintenance Engineer at Tipa Petroleum ServicesCairo, Egypt
Graeme hunter
Value-based Healthcare Portfolio Manager at CTMUHBUnited Kingdom
Hicham tliba
Testing Data Acquisition (TDA - DAQ) Field Engineer @ Expro | Surface Well TestEl Oued, Algeria
Shashank sood
atGreater Delhi Area
Melanie salinas rosales
TP Senior Advisor- SKATTMexico City, Mexico
Ryan thrower
Associate - Digital Engineering Coordinator at WSP in AustraliaGreater Sydney Area
Rami abuhalaweh
Senior Project Controls specialistالشرقية الخبر السعودية
Andaç aydin
Diplom InformatikerFrankfurt Rhine-Main Metropolitan Area
Mingya xia
Product Operations Manager - Supply Chain at Alibaba GroupSan Francisco Bay Area
John bauer
IT Project Manager - Scrum Master - IT OperationsSan Francisco, California, United States
Hirushani umayanga
Temporary Lecturer|B.Sc(Hons) in Computer Science | Software Engineer |Microsoft Dynamics NAV | Web ...Gampaha District, Western Province, Sri Lanka
Juan donaire
Director de Explotación GB HotelesBenidorm, Valencian Community, Spain
Pooja kadam
Assistant Manager - Designer/Analyst of Cured Tire at MichelinPune, Maharashtra, India
Medha nag
PhD Research Scholar at Indian Institute of Technology, KharagpurKolkata, West Bengal, India
Massimo bellomo
Director of Business Unit Integration at H-EnergyMonza e Brianza, Lombardy, Italy
Lav prajapati
EIT - Civil/Structure @ REMISZ | RCC/Steel Structures | Field Engineering | BIM | WES CertifiedOttawa, Ontario, Canada
Deden disa abdulllah
Environmental Engineer | K3 & Lingkungan Spesialis | Manager Energy Certified | Auditor SMKP ESDM Ce...Jawa Barat, Indonesia
Shahriar rabbi
Banker | ERP Operation Management | BI Tool Management | Application Specialist | Database Managemen...Bangladesh
Agnibha joardar
Lead Business Analyst at Happiest Minds | ex- InfosysBengaluru, Karnataka, India
...