
Taylor Rea

Connect with Taylor Rea to Send Message
Connect
Connect with Taylor Rea to Send Message
ConnectTimeline
About me
Pipefitter Foreman | Pipeline Consultant | Red Seal Steamfitter/Pipefitter
Education

Ua Piping Industry College
2012 - 2013Steam Fitter Ticket Steam Fitting
Pacific Vocational College
2006 - 2010Fire Sprinkler Ticket Fire Prevention and Safety Technology/Technician.webp)
Southern Alberta Institute of Technology (SAIT)
2018 - 2018API 1169 General Inspector
Experience

The Gisborne Group
Jun 2006 - Nov 2010Wolverine Yukon zinc mine► Responsible for installation of piping, pumps, conveyors, ball mills, and structural steel. Performed conveyor repairs of the head/tail/snub/counter pulleys/counterweights, the loading transfer return and belt idlers. Univar chemical plant train and port facility for ethanol and acoustic soda Diavik diamond mine process buildings Weyerhaeuser saw mill Instillation/Maitnence of fire sprinklers in residential commercial and industrial settings.
Pipefitter
Sept 2009 - Nov 2010Pipefitter
Jan 2009 - Sept 2009Pipefitter
Jun 2008 - Jan 2009Pipefitter
Sept 2007 - Jun 2008Fire Sprinkler Installer
Jun 2006 - Sept 2007

CT Fire Protection
Jan 2011 - Mar 2012Co Owner
Kiewit
Mar 2012 - Jun 2012PipefitterKiewit mod yard

JV Driver Projects Inc.
Jun 2012 - Sept 2014Nabiye SAGD processing plant for imperial oil. Highland valley gold and copper mine floatation expansion. Suncor Williams energy site.
Pipefitter Foreman
Feb 2014 - Sept 2014Pipefitter Foreman
Mar 2013 - Feb 2014Pipefitter Lead Hand
Jun 2012 - Mar 2013

PCL Construction
Sept 2014 - Feb 2015PipefitterAgruim pot ash mine

JV Driver Projects Inc.
Feb 2015 - May 2015PipefitterSAGD processing plant and co gen facilities for shell.

CIMS Limited Partnership
May 2015 - Jun 2015PipefitterSpectra energy sour gas plant

JV Driver Group
Sept 2015 - Mar 2017Jacos SAGD processing facility► Ran 6 crews with 10-12 people per crew (2 welders per crew). At end of project oversaw crew of 12 people comprised of pipefitters, millwrights, instrumentation, and glycol heat tracers to perform deficiency work and small amounts of commissioning.► Utilized computer skills to do time sheets, rfis, and progress reports. Handled a variety of activities spanning critical lift plans, operation permits, weld mapping, making work packs, attending daily meeting with other trades/supers, and client reps.► Provided all install and testing of process and utility piping/supports/testing/install of pumps and commissioning with millwrights. Maintained good relations with on-site contractors on site to have work performed, such as scaffolding. Show less
Pipefitter General Foreman
Jul 2015 - Mar 2017Pipefitter
Sept 2015 - Sept 2015

Thompson Valley Erectors
Sept 2016 - Nov 2016PipefitterMerritt Green Energy Project Boiler and Turbine

IDL Project Management
Mar 2017 - Apr 2017PipefitterNorth Wood Pulp Mill Shutdown► Ran a crew of up to 5 people on a shutdown where we had to pull out 2 -42” knife gate valves in an underground pit. These valves would discharge the influent ponds. Organized operations permits (written and signed-off); held meetings; and worked with cranes to remove and install new valves.

Aecon Group Inc.
Apr 2017 - Dec 2017Pipefitter Foreman (April 2017 to December 2017) / Pipefitter (June 2017 to August 2017)Aecon – 8A/6B Enbridge Compressor Stations ► Tasked with running crews up to 25 pipefitters and 5 welders for a project to upgrade natural compressor stations. Remained with the project until the end, working closely with operations and helping with commissioning activities. ► Worked with the supers and general foreman to create a daily plan to be executed and perform toolbox. Tasked to write-up and have all permits approved and signed by operations for work each day. ► Worked with coordinators and quality control to get red lining as-built welding procedures and documentation signed-off and approved for turnover.► Utilized cranes, zoom booms, and other equipment to facilitate the install of all new pipes and compressor for the multiple tie-in points to the existing pipeline and facilities.► Hydrotesting was performed on all lines with water samples taken of all water on-site and approved by operations to be used or discharged. ► Monitored and wrote permits for multiple other contractors to facilitate access to site such as hydro vac/water trucks/fuel trucks/material delivery/site services. Show less

TC Energy
Nov 2017 - nowPipeline ConsultantMaitnence/Shutdowns/Pigging/Operations

Black Angus Mechanical
Oct 2020 - nowPipefitterQuesnel River and Cariboo Pulp shutdowns

Bird Construction
Mar 2021 - May 2021Pipefitter Foreman► Provided strong, decisive leadership to crews at max of up to 25 people (4 of them welders) on a new construction project with approx. 12 tie-in points to the existing facility. Installed/tested and commissioned all process piping and pumps to facilitate unloading of diesel (trains to tanks) and loading (onto ships).► Oversaw installation of fire suppression foam water cannon system. Took on a civil role in building and decommissioning a temporary containment berm due to the facility still being in operation.► Utilized industrial air compressors to send foam pigs down the underground section of the diesel line to remove trapped water from hydro testing. Installed kilometers of welded track pan to catch spilt diesel from the trains.► Worked with crane operators to facilitate any lifts needed, some of which were considered critical due to the sections of the terminal in which work was being conducted.► Collaborated closely with day shift supers and general foreman in making detailed plans. Held toolbox meetings with operations and the workers to go over tasks to be completed. Spoke to each group individually with more detailed information on the task and signed FLHA cards.► Prepared detailed progress reports and weld mapping. Filled out operation permits to be approved by Pembina for the work to be done each night. Show less
Licenses & Certifications

API 1169 General Inspector
API 1169 General Inspector
Pursuing studies toward completion of the Blue Seal construction management course.
Pursuing studies toward completion of the Blue Seal construction management course.
Red Seal Steamfitter/Pipefitter
Red Seal Steamfitter/Pipefitter
Recommendations

Samuel vasquez, pacs
Case Manager @ Amicus TherapeuticsKunkletown, Pennsylvania, United States
Brian curle
RetiredLinlithgow, Scotland, United Kingdom
Smit thummar
Student NMIMS || Summer intern ICICI Prudential AMC || NISM series-VIII || NISM series V-A || CFA L-...Mumbai, Maharashtra, India
Viswanath palepu
Delivery Manager at WiproHyderabad, Telangana, India
Robin lanae brown
HR ProfessionalSan Francisco Bay Area
Ca bhupesh saxena
Senior relationship manager MNC Group- ICICI BankBhopal, Madhya Pradesh, India
Prabhakar yadav
Senior Technical Engineer (Cyber security) at Hitachi Systems India Pvt LtdNew Delhi, Delhi, India
Paul nesbitt
Retired military looking to find gainful employment.Port Alberni, British Columbia, Canada
Anusha e
PMO ServicesChennai, Tamil Nadu, India
Naya paramahita
Tax Specialist PT Integrasi Teknologi Unggas (BroilerX)Yogyakarta, Indonesia
Amy nguyen
Director of AMA DANANG EDUCATION JSC. CEO/ CMO/COOVietnam
Muhammad junaeed akbar acs
Senior Officer, Local Office at Islami Bank Bangladesh LimitedBangladesh
Daniel cho
--Centreville, Virginia, United States
Venkatesh kurni
Certified Kubernetes Administrator | Principle Linux Engineer at SalesforceBangalore Urban, Karnataka, India
Ashwini t n
HRIS Analyst I at Rakuten IndiaBengaluru, Karnataka, India
Mounira nageh
Quality Control Engineer at Link Development | ISTQB® - CTFLGiza, Al Jizah, Egypt
Hui zhang
R&D Manager at NokiaHangzhou, Zhejiang, China
Manjeet kaur
Senior Finance Executive at ONB TECHNOLOGIES PVT. LTD. (21 NORTH)Bengaluru, Karnataka, India
Sarah qureshi
Dental Surgeon ,Medical Educationist and a TeacherJazan, Jizan, Saudi Arabia
Soliman alrebdi
Conformity Engineer Assistant at GSO | Electrical Engineer | ISO 9001 Lead Auditor | Data Analysis |...Riyadh, Saudi Arabia
...