
Nuno Baptista Matos
Project Engineer / Deputy Project Manager / Project Manager

Connect with Nuno Baptista Matos to Send Message
Connect
Connect with Nuno Baptista Matos to Send Message
ConnectTimeline
About me
Construction | Project Manager, PMP at ACCIONA - Dubai Metro Route 2020
Education

Universidade de Coimbra
2013 - 2014Post-Graduation Principles of Economics
Católica Lisbon School of Business and Economics
2011 - 2011Executive Education / Post-Graduation Advanced Management Program for Construction
Universidade de Coimbra
1999 - 2005Master of Science (MSc) Civil Engineering - Specialization in Structures
Université de Liège
2004 - 2004Civil Engineering - Socrates / ErasmusExchange Program
Experience
%20%2F%20Mecanotubo%20J.V..webp)
VSL (Bouygues Group) / Mecanotubo J.V.
Dec 2005 - Dec 2009Project Engineer / Deputy Project Manager / Project Manager• Project: Marão Tunnel Highway Concession - €425m / US$629• Principal Features: Execution of two cast in-situ reinforced and post-tensioned concrete double deck viaducts, one overpass, two underpasses and the structural reinforcement and widening of five existing highway structures.• Project: Grande Lisboa Highways Concession - €256m / US$366m• Principal Features: Execution of fourteen overpasses, eleven underpasses and three pedestrian passes, totalling twenty eight new highway/railway structures, as well as the structural reinforcement and widening of two existing passes and the demolition of another two ancient overpasses. Very strict rail rules and regulations were also applied given the interferences with live railway lines (West and Lisbon-Sintra, the busiest in the country). Construction methods covered cast in-situ reinforced and post-tensioned concrete deck, pre-cast concrete deck and composite steel and concrete deck erected by incremental launching. Building and management of a pre-cast yard to produce about 3, 8km of pre-cast/pre-stressed reinforced concrete beams. Construction of reinforced earth retaining walls, totaling a surface of 4800m2.• Project: Construction of the highway “IC13 - Alter do Chão / Portalegre” - €35m / US$50m• Principal Features: Execution of six bridges, ten overpasses and two underpasses totaling 885m of post-tensioned and reinforced concrete deck.• Project: Norte Highways Concession - €1570m / US$1978m• Principal Features: Execution of Bôco Riverside Viaduct and Torno River Viaduct with double concrete deck pre-cast system, including yard production of pre-stressed/pre-cast reinforced concrete beams.• Project: Construction of the highway “IC9 - Alburitel / Tomar (IC3) - €27m / US$32m• Principal Features: Execution of two bridges and four cast in-situ viaducts totaling 1350m of reinforced and post-tensioned concrete double deck, five overpasses and six underpasses Show less
.webp)
Dragados (ACS Group)
Sept 2012 - Feb 2013• Project: Baixo Alentejo Highway Concession - This Trans-European Transports Network Project (TEN-T) concerns the design and construction of 68 km of a new highway, widening and/or adaptation of 59 km of an existing road to highway standards, and improvements of 149km of an existing road as well as the transfer of responsibility during a 30 years period for operation and maintenance for 71km of existing road forming a 347 km long road network in the south of Portugal. • Total Investment: €690m / US$979m (funded by the EU / European Investment Bank / Loan Guarantee Instrument for TEN-T Projects (LGTT))• Promoter: IP (Portugal Highways and Rail Agency) / Estradas da Planície • Sub-Project: Construction of the highway “Auto-Estrada do Baixo Alentejo, Lanço B - Nó de Grândola Sul (IP1) / Ferreira do Alentejo e Lanço C - Ferreira do Alentejo / Beja”• Main Contractor: RBA / Dragados (ACS Group)• Principal Features: Execution of a 45km long stretch of the Baixo Alentejo Highway, comprising, earthworks and slope stabilization, drainage, pavement, signaling and highway structures with particular emphasis on pre-stressed/pre-cast reinforced concrete deck viaducts and overpasses, cast in-situ reinforced and post-tensioned concrete deck overpasses, and pre-cast and cast in-situ reinforced concrete underpasses, totaling over 30 new structures. Show less • Project: “Amoreira-Caliços Hydraulic Circuit” (Primary Irrigation/Water Supply Network) - Construction of Amoreira pumping station, Caliços dam and Amoreira-Caliços pipeline. Estimated Contract Value: €27m / US$34m (funded by the EU)• Project: “Cinco Reis-Trindade - Irrigation, Road and Drainage Infrastructure” (Secondary Irrigation/Water Supply Network) - Construction of Cinco Reis filtering station and reservoir, Cinco Reis-Trindade pipeline and gravity irrigation network. Estimated Contract Value: €27m / US$34m (funded by the EU)• Promoter: EDIA (Alqueva Hydroelectric and Irrigation/Water Supply Infrastructures Agency)• Main Responsibilities: Supporting the technical-commercial department during the tendering phase, performing project technical analysis and preparation of procurement documents. Procurement process advertising, promotion of bidder conferences and evaluation of proposals received from prequalified subcontractors. Direct and indirect cost estimation and composition of cost baseline and final project budget. Show less
Project Manager
Jan 2010 - Feb 2013Tendering Engineer
Sept 2012 - Nov 2012

CMI
Mar 2013 - Mar 2014Technical and Financial Adviser (External)• Supporting the Management decision making regarding the development of the Company’s core business since its establishment in 1984 (design, construction, maintenance and rehabilitation of public and private buildings) from an organizational, technical and financial perspective. This consultancy role was performed in parallel with the attendance of a Post-Graduation in Economics at the University of Coimbra.
.webp)
Six Construct (Besix Group)
Mar 2014 - Sept 2016• Project: Dubai Water Canal - The canal is allowing navigation around Dubai, giving access to the most prestigious ancient and new districts, through modern water transport facilities, whilst simultaneously creating a new waterfront development.• Value: AED1.048m / US$285m • Promoter / Client: Dubai - Roads and Transport Authority (RTA)• Engineer: CH2M Hill (Halcrow) / Parsons• Main Contractor: Six Construct (Besix Group)• Principal Features: The scope comprises the construction of a 3.2km long and +-100m wide waterway, including the development of a marina within a 1.5km new peninsula reclaimed in the sea. The banks side of the canal are built with pre-cast mass concrete blocks and a 720m long diaphragm wall on the south side forming quay walls. Three iconic pedestrian bridges are linking the two sides of the Canal at key locations. Show less • Project: Qatar Gabbro Terminal Expansion - To support the growing demand of aggregate cargo for Qatar´s infrastructure development ahead of FIFA World Cup 2022, the capacity of the bulk materials import terminal in the Port of Mesaieed required an increase to thirty million tonnes per annum. The project was delivered through an industrial EPC + Commissioning contract (FIDIC - Yellow Book) for the installation of a new four stream conveyor system to transport bulk aggregate materials from the existing shore cranes at berths 2 and 3 to six new movable stackers running along 6km of rails at QPMC stockyard. Truck discharge hoppers were also installed in the corridor area to receive material from Berth 1 and the barge facility. Oil&Gas industry rules and regulations were strictly followed provided the project was developed within QP/MIC restricted area.• Value: QAR1.200m / US$329m • Promoter / Client: Qatar Primary Materials Company (QPMC) / Qatar Petroleum (QP) / Mesaieed Industrial City (MIC)• Engineer: Aurecon• Main Contractor: Consortium Six Construct (Besix Group) / FLSmidth• Principal Features: Engineering, fabrication and erection of >10.500Ton of structural steel totalling 23km of conveyor bridges and hopper building, installation of >14.000Ton of mechanical equipment including 6km of rail system (8m gauge) supported by diam.1500mm piles and pre-cast concrete beams forming the stacker line bunds. Stockyard soil improvement with 1.300km of vertical drains and soil replacement by 1.1Mm3 of imported engineered fill. Design-build of two control buildings, two 33kV primary substations, five 11kV secondary substations, >11km of roads, drainage / waste water treatment and utilities. Commissioning of the complete civil, mechanical and electrical system. Show less
Bridges & Special Structures Manager
Jan 2016 - Sept 2016Technical Manager / Deputy Project Manager
Mar 2014 - Jan 2016

Educational Institution
Oct 2016 - Aug 2017Project Manager• Projects / Key Responsibilities: Provision of freelance project management services to private companies and public entities requiring support while engaging with design and construction companies to meet their business demands.

ACCIONA
Sept 2017 - nowViaduct Manager• Project: Dubai Metro Route 2020 – The project involves the design and construction of a 15km long line, of which 11,8km of elevated metro line and 3,2km underground metro line - branching off the existing red line at the Nakheel Harbour & Tower station. The metro extension comprises seven stations, including an interchange at Nakheel Harbour and an iconic metro station at the World Expo 2020 site. • Value: AED10,6bn / US$2,8bn• Promoter / Client: Dubai - Roads and Transport Authority (RTA)• Engineer: Parsons / Systra• Main Contractor: Expolink Consortium (Alstom, ACCIONA and Gulermak)• Principal Features: This highly-complex project includes a 3,2km tunnel perforated by a tunnel boring machine (TBM), 1,2km of open-cut route and 11,8km of elevated viaduct metro line. The viaduct substructure comprises 851 piles, 372 cast in situ piers, 47 cast in situ pier caps, 33 cast in situ portals and 259 precast pier caps produced in the project pre-cast yard, along with 3174 deck precast segments. The superstructure segments are erected with four launching gantries (9,1km), balanced cantilever method (lifting frames and/or crane) at seven locations (756m) and falsework (1,2km), whereas about 680m of deck are cast in-situ. The connection with the existing red line requires partial demolition of the ancient viaduct and further construction of a combined cast in-situ structure (tie-in). Show less
Licenses & Certifications

Project Management Professional, PMP®
Project Management Institute
Chartered Engineer, Member of Portuguese Institute of Engineers / European Council of Civil Engineers
Ordem dos Engenheiros
Honors & Awards
- Awarded to Nuno Baptista MatosCertificate of Appreciation Dubai - Roads and Transport Authority (RTA) 2018 Sincere gratitude and appreciation in recognition of Nuno Matos valuable contributions and efforts in managing the viaduct works related to Metro Route 2020 Project
Languages
- poPortuguese
- enEnglish
- frFrench
- spSpanish
Recommendations

Alana garcia prieto
Sales + Marketing Assistant, Intero Advisory | Cultivating Deep + Dynamic RelationshipsSan Salvador, El Salvador
Paweł majewski
Senior Data Scientist | Computer Vision | Researcher | PhD CandidateWroclaw Metropolitan Area_Chen.webp)
Yenfei(phoebe) chen
Financial Accountant | | MS in Finance at UIUCPhoenix, Arizona, United States
Stéphanie prédot
Responsable communication digitale | Communauté d'Agglomération de Rochefort OcéanTrizay, Nouvelle-Aquitaine, France
Jan willem van der helm
Program Manager Industrialization at NXP SemiconductorsBrabantine City Row
Maria perez
Studio Manager-ExpressCorona, California, United States
Igor silva de oliveira
Tecnologia da Informação | Governança | Infraestrutura | SuporteFortaleza, Ceará, Brazil
Marcela cerqueira lima
Coordenadora de Marketing no Via Vale ShoppingTaubaté, São Paulo, Brazil
Antonio miguel pérez rivera
Software Engineer - Java/Magnolia CMS en Knowmad MoodJerez de la Frontera, Andalucía, España
Kim tran, mbcp
Senior Service Delivery Manager - Managed Cloud ServicesGreater Houston
Yong yang
Project ManagerNanjing, Jiangsu, China
Stefan bosch
National Sales Manager bei Rada Armaturen GmbHBadbergen, Lower Saxony, Germany
Franc-paul koppel
Production Manager at NOTEEstonia
Laura hernández eberhard
Marketing Social Media Manager at iLovePDFSpain
Marinella marconi
Systems Engineer - Helicopter Transmissions presso Avio Aero - a GE Aviation BusinessItaly
Joseph siragusa cfp®
Vice President/Branch Leader-Fidelity Investments Knoxville/ChattanoogaKnoxville, Tennessee, United States
Takashi managaki
HR Manager at LVMH Watches & JewelryJapan
Ligia-mihaela ciurel
Senior HVAC Design Engineer, Verificator de proiecte si expert instalatii termice It MDRAP la Ligia-...Bucharest, Bucharest, Romania
Marina peter
Company Secretary & Compliance Officer - Orchid Pharma LimitedDelhi, India
Shaffik yaroub
Network engineer experienced in technical career IT, Telecom (Core network, Radio) and project manag...Iraq
...