
Nathan Roberts ChPP
Land Surveyor & Setting Out Engineer

Connect with Nathan Roberts ChPP to Send Message
Connect
Connect with Nathan Roberts ChPP to Send Message
ConnectTimeline
About me
Project Director at Turner & Townsend
Education

Hurstpierpoint College, Hassocks
1989 - 1994A-Levels English, Geography, Economics
University of East London
2004 - 2006R.I.C.S Finals Large Scale Metrology & Cadastral Surveying
University of East London
2002 - 2004HNC Surveying & Land Management
Experience

Maltby Land Surveys Ltd - Based in Sussex
Jan 1995 - Jan 2005Land Surveyor & Setting Out EngineerSetting Out Engineer:2005: Brighton Station NEQ (New England Quarter). Setting up Primary control for the whole site, setting out of all roads and main drainage along with incoming services for suppliers. Cut and fill quantities.2005: BMW / Rolls Royce Manufacturing Plant Chichester. Worked direct for BMW as senior engineer setting out primary control, checking all RC piles setout, and holding down bolts. Checking verticality of all structural steel work. Setting out all earthworks, surveys to establish cut and fill quantities. 2003: Longham Lakes Poole. Worked direct for F.L.Gamble & Sons converting an old quarry into raw water storage reservoir. Setting out sides of reservoir batters 35m in height with two different materials and a clay cap. Setout of intermediate bund to allow project to be completed in two phases. Dewatering and soft landscaping. Volume calculations of materials imported and exported.2003: Bolnore Village Haywards Heath. Worked direct for F.L.Gamble & Sons establishing primary control, setting out for 3km of bypass road and local village roads. Digging to formation level for the first two phases of 150 houses.2002: Gun Wharf Quays. Worked direct for F.L.Gamble & Sons, setting out for excavations and pilling. Volume calculations for materials excavated.2002: Paddington Station. Complete 3D CAD surveys of station prior to refurbishment, including platform and roof survey for rights of light issues.2002: London Docklands Light Railway. Checking for level and alignment of 7km of new installed railway lines.2002-1998: Summerset, Lake District, Eastbourne. Hydrographic Surveying and Modeling for the Environment Agency. Show less

ADENSTAR DEVELOPMENTS LIMITED
Jan 2005 - Aug 2008Senior Setting Out EngineerSenior Setting Out Engineer:2007: T4 Heathrow West Base. Demolition of 50,000m2 of old hangars and overlaying with Asphalt and applied Densiphalt, installation of drainage and services, FEGP’s, Taxiway and stand markings.2006: The Galleries Hove. Barratts Homes. Setout 150m of contiguous piled wall to create 75 space underground car park, podium slab on top. Two RC frames 6 floors high for each and envelope. 2005: International Language School Balfour Beatty. Brighton. RC piles and foundations, creation of podium slab and walls to first floor level and associated drainage.2005: Brighton Station NEQ. Demolition of all roads and existing buildings. Setting out of 14 RC frames from 6 – 14 Floors. 450m of contiguous 650mm dia piled wall (35m in height). Podium slab, all drainage hard and soft landscaping, full envelope and fit out of flats. Sainsbury supermarket and 250 space underground car park. Show less

Dyer & Butler
Jan 2008 - May 2012Senior Site Agent;Looking after Construction Projects at the Airport.2012: Nights Maintenance Manager, Supervising all works landside and airside on nights.2011: Costain - Taxiways & Cul-de-sac Rehabilitation Works. The project was to be carried out on Days / Nights at Various Locations Airside at Heathrow Airport: Block 57 Outer, Golf Cul de Sac, Block 34 Inner, Delta South and Block 99. The works typically comprised of the following items (non exhaustive); Aircraft Pavements, replacement PQ Bays. Communications and Electrical Duct Work; Chambers and Structural Repairs. Pits and Covers including Confined Space Works. Installation of AGL’s. Re-Alignment of Taxiway Centerlines. Paint Markings to Roads and Airfield Pavements.2011: Costain - Eastchurch Crossing A380 Enabling Works.2011: Kier - Road Reconstruction, Asphalt and Glasgrid with Antiskid surfacing and White Lining2010: BAA - Reconfiguration and resurfacing of roadways in BAA Northwood Road Car Park involving full depth road reconstruction, kerb alignment, signage and road markings. Show less Site Agent : Dyer & Butler, Gatwick Airport.Site Agent running a project from start to finish, beginning at the planning stages right through to finalization of accounts. I was accountable for controlling costs, writing method statements and risk assessments, overseeing sub-contractors, allocation of plant, labour and resources. Agents perform weekly safety inspections and DABBS (Dyer & Butler behavioral safety). Liaising with airfield and external operations, GAL EDM, and any BAA project managers.Pier 2 Reconfiguration. The Airfield works was over a 60 week period costing just over 1 million pounds included facilitating the downgrading of 9 Code “D” stands to 13 Code “C” stands the following works were carried out: Full depth reconstruction of circa 2,800m² of airfield pavement (400mm PQ concrete on 150mm lean mix on 300mm type 1), Excavation for subsoil drainage, new catch pit construction and Removal of all existing line markings and in house repainting of all aircraft stand markings to new layout. Pier 2 Reconfiguration Fuel Main Works. The project was over a 60 week period included facilitating the downgrading of 9 Code “D” stands to 13 Code “C” stands the existing fuel hydrant points required relocating and increasing. Breaking out of PQ concrete and excavating down to the existing fuel main to enable GASHCO to weld on and modify pipe work, reinstate apron on completion of works. £750,000 of work over five phases; consisting of 12 new fuel hydrants and 12 redundant hydrants to be capped off. Excavations depths ranged from 1.0m to 2.5m deep with temporary works designed for each. Confined space entry to facilitate works on the live Fuel main. Show less
Senior Site Agent - Heathrow Airport
Apr 2010 - May 2012Site Agent - Heathrow & Gatwick Airports
Jan 2008 - Jun 2011

VolkerFitzpatrick Ltd
Mar 2012 - Dec 2014Project Manager on the Gatwick Flood Attenuation Scheme.Creation of 186,000 m3 Flood Storage Area within Gatwick Airport:The Main Activities are as follows:· Construction of a flow limiting control structure within the Gatwick Stream upstream of the airport,designed to restrict the flows downstream of the structure to 15m3/s. This will be a concrete structure incorporating cast iron / steel twin control gates.· Excavation of c.160,000m3 of soil from the fields in the land alongside the Gatwick Stream immediately upstream of a proposed control structure, bunding of the excavated area, and then restoration of the whole site to g razing land which will, together with the formation of embankments along the western and eastern boundaries of the flood storage area, create a storage ‘reservoir’ capable of holding c.186,000m3 of floodwater· Removal of 150,000m3 of the excavated material from the site.· Diversion of a section of the Gatwick Stream and engineering of embankments to form a floodwater inlet to the storage area during high river flows and a simple outlet structure upstream of the control structure for water to return as flows recede.· Construction of a pumping station adjacent to the control structure to remove water collecting from direct rainfall in the storage area to the Gatwick stream as well as residual flood water.· Construction of a vehicular maintenance access route to the control structure, which is to be incorporated into the new embankment.· Construction of a single storey 6m x 4m control building next to the maintenance access route.· Extension of the permissive footpath network, including a new footbridge over the Gatwick Stream.· Landscape and Ecological enhancement measures including restoration of the site to grazing land, new tree planting (approx. 2000 trees) and reinstatement of hedgerows (approx. 540 linear metres). Show less Project Manager on Days for Main Runway Rehabilitation Project:The project involved resurfacing an area of 400,000m² - with approximately 70,000t of asphalt. Around 1.900 runway and taxiway lights, fed by 530km of electrical cabling, will also be replaced. Carrying out work on Gatwick's main runway was a major challenge with up to 53 aircraft landing and taking off every hour. In order to keep the runway operational all resurfacing and associated works from March to December 2012 was undertaken during possessions. With just seven working hours VolkerFitzpatrick removed and replaced about 130m of runway at a time. While the runway rehabilitation was being undertaken it provided an opportunity for other improvements to be delivered for example: Installation of a new aeronautical ground lighting control system, Ehancement of the existing runway guard bar system, Replacement of cabling and switches, replacement of Constant Current Regulators, Provision of a new secondary duct system within the pavementProvision of additional pit and duct systems Show less
Senior Project Manager
Mar 2013 - Dec 2014Senior Project Manager
Mar 2012 - Feb 2013

Turner & Townsend
Oct 2014 - nowWorking on the YVR CORE Program, Vancouver International Airport Senior Project Manager, Stansted Transformation Programme Phase 1. A380 Wide bodied enabling works Senior Project Manager for Airside / Landside Developments Q6 Works. Working on various Business Cases such as; Airport Resilience, Asset Replacement & Life Safety Systems. Taking business cases through the Heathrow Gateway Cycle (Aligned with RIBA) through to successful delivery, completion, commissioning and handover.
Aviation Sector Lead PM South East
Apr 2023 - nowProject Director
Sept 2021 - nowProject Management Services Lead Heathrow Airport
Sept 2021 - nowAssociate Director Canada
Sept 2017 - Nov 2021Associate Director
Jul 2017 - Oct 2017Associate Director
May 2016 - Jul 2017Senior Project Manager
Oct 2014 - May 2016
Licenses & Certifications
- View certificate

Chartered Project Professional (ChPP)
Association for Project ManagementJan 2023
Volunteer Experience
Assistant Section Leader
Issued by The Scouts on Jan 2022
Associated with Nathan Roberts ChPP
Recommendations

Hossam medhat
Mobile App Developer | Flutter @ AMHZ International Group REGOCairo, Egypt
Priyadarshani bhamare. istqb®
ISTQB® | Software Testing | Test Management | Defect Management | Manual Testing | Agile Testing | S...Pune, Maharashtra, India
Rafael a. castillo
EMPORIO GLOBAL RADIOSanto Domingo, Distrito Nacional, República Dominicana
Girubaraj balaravisekar
Associate Vice President & Branch Head at THE FEDERAL BANK LIMITEDChennai, Tamil Nadu, India
Chloé dujardin
Coach ICF | Business Trainer | Instructor MindfulnessLiège, Walloon Region, Belgium
Margaret foss r.n.
Registered Nurse at Evergreen Adult Day HealthcareGreater Boston
Buğra kocadağ
Sterilization Manager at GetingeTürkiye
Shashank yadav
Technical RecruiterUnited States
Ulfah khoerul umah
Analyst Credit | Customer Service | Administration | Teller | Document Controller | Call Center | Fr...Malang, East Java, Indonesia
Samuel maia
Executivo de Saúde | Gerente de Operações | Administrativo | Comercial | SuprimentosBelo Horizonte, Minas Gerais, Brazil
Jennifer biecar
Accounts Assistant & Office SupportNelson, Nelson, New Zealand
Todd tressler
Audio-Visual ProfessionalAdrian, Michigan, United States
Katy rodberg, msn, apnp, fnp-bc
Nurse Practitioner Internal MeciconeMenomonee Falls, Wisconsin, United States
Azadur rahman azad
ETP AUTOMATION CONSULTANT, WASTE WATER MANAGEMENT EXPERT, ETP & WTP REMOTE MONITORING SYSTEM DEVELO...Dhaka, Bangladesh
Agnes hertogs
Chief Executive Officer at INFINO ...Brussels Metropolitan Area
Pradip sable
IIoT | Industrial Automation | MES | PTC Thingworx | Rockwell Software | KepserverEXPune, Maharashtra, India
Valerie vander loop
Fortrea RISE & Global Internship Program ManagerGreater Madison Area
Chris garlock, cpa, ca
Finance ExecutiveGreater Toronto Area, Canada
Simran saini
Surrey, British Columbia, Canada
Maria canton-rello
Information Technology and Management M.A.S @ IIT | Telecommunications Engineering MEng @ ETSIT-UPMChicago, Illinois, United States
...