
Timeline
About me
Construction Manager at Bin Quraya Limited Company
Education

Al-neelain university
2007 - 2012B.sc. control and instrumentation engineering overall rate 79.76%
Experience

Sendan international co. ltd.
Sept 2013 - Oct 2016Instrumentation engineerProject : SADARA PROJECT Working as Instrument Field Engineer for the construction of Saudi Aramco & DOW Arabia joint venture project of SADARA ISOCYANATES CHEM II (Toluene Di Isocyanates - TDI)• Leading a team of Construction Supervisors, Foreman & Inspectors for installation and commissioning of field instruments ( FT,LT,PT,TT, Control valves,,etc) and control systems equipment and cabling work .• Provide technical assistance to construction team.• Preparation of the As-built in Instrument drawings. and coordination with designing team • Monitor the financial performance.• Material take-off (MTO) from IFC drawings & preparation of progress monitoring techniques.• Manpower planning and estimation schedule, conduct, and coordinate program of assigned engineering work and project control.• Review material receiving reports and warehousing to assure delivery of correct materials.• Assists co-workers with installation & maintenance of structured cabling systems as well as Instrument equipment’s such as Different types of Panels & Transmitters, Junction Box, Cable tray and Field instrument installation.• Leading the Calibration Lab Team & loop Testing Team and preparation of loop folders for control loops (FF & HART). • Install Pneumatic line for control valve, and process and sampling tubing (Impulse and analyzers)• Direct Supervisor for all activity in process interface building (ABB marshaling panels, I/O cabinets and controller cabinets installation and main cable + system cable termination • Develop & execute of weekly progress plan. Show less

Arkad engineering & construction company
Nov 2016 - Oct 2019Sr. project engineer (e&i)Project: Onshore Maintain Potential Program (OMPP) ‐ Saudi Aramco Northern Area Oil Upstream Projects NA-1 & NA-2*Responsibilities: Responsible of all electrical and instrumentation works in the project.Engineering: (review the IFC packages and CRPOs, material take-off, initiate the MR for the required material and tools as per the aramco codes, arrange all documents required by client for the material NMR's and else, making the redline/As-built of the drawings, initiate technical queries TQs for required matters, Project close out)Construction: (Supervise all site construction activities, manpower control and planning, coordination with inspection team, insure the construction activities meeting the HSE requirements, coordinate with the planning team to achieve the target completion schedule, reporting all construction steps to the direct manager, preparation all energization packages and loop folders, Perform the calibration of all instrument, pre-commissioning and SAT for the equipment/ panels and instruments)*Details of the work: •Cathodic protection of well head casing and pipeline (Cable installation, Anode Installation and JBs, drilling of deep anode well, testing and commissioning of CP system)•Overhead power line (supply) to the new wells OHPL 34.5kV - 13.8kV. Installation Including testing and commissioning.•Power and instrument cable installation.•Groundings system, Tower light, Corrosion Inhibitor Skid,• Instrument Installation (PT, TT, FT, MOV, MCV.) Gas detractors LEL/H2S.• Installation of I-Field instrument in upstream fields (PDHMS, MPFM, UFM, SWC) •Installation of RTU, UPS System, Fire alarm and configuration with vendors, SCADA configuration.•Commissioning and startup of well system including MPFM calibration and commissioning•Installation and testing the local / remote shutdown system for the wells and Installation of corrosion monitoring systems CMS.•Installation of ESP skids . Show less

China petroleum pipeline engineering co.,ltd.
Oct 2019 - Jun 2021Lead electrical engineerProject: Saudi Aramco North Gas Compression Plants Pipelines (NGCP) BI-10-02029-0003 - LSPB Haradh and Hawiyah Gas Compression Fields(Project summary): The purpose of the gas compression facilities is to increase production by reducing the wellheads backpressure from above 600 psig to about 300 psig.The facilities: 190 OPTFs (off plot tie-in facilities) , 2 GGMs (gas gathering manifolds), 26 RHs (remote headers), 3GCPs (gas compression plants), 1 LSS (liquids separation station), 2 Valve stations, 900 km pipelines, 60 km OH power lines (Electrical works): Providing the power supply/OHPL to the new/expanded facilities like Remote header, Gas gathering manifolds and Valve stations.-Installation of all types of cables MV/LV , new area lighting and solar lighting systems.-Installation and commissioning of new switch racks,panel racks, battery systems, CP / ICCP systems and MOVs. Show less

Bin quraya
Jun 2021 - nowProject : BI-10-12322 ZULUF AH. CRUDE DEVELOPMENT PROGRAM - WATER SUPPLY FACILITIES ( LSTK / EPC )Summery : This Project to develop 8 Drill sites, which shall include the installation of the followings:• Fifty (50) wells powered by Electric Submersible Pumps (ESPs)* distributed across Eight (8) Drillsites.• Thirty two (32) chemical injection systems consisting of (8) each of Corrosion Inhibitor, (8) Scale Inhibitor, (8) Oxygen Scavenger and (8) Biocide Injection skids as total for all drill site.• 23 KM of Overhead power lines (13.8kV) from Marjan Substation-202 to all drill sites. • Twenty four (24) 13.8kV outdoor switchgears.• Twelve (12) Remote Terminal Units (RTU) which shall interface with the SCADA at Zuluf CPF.• Two (2) 50/66.67 MVA POWER TRANSFORMER 115/13.8kV, and one (1) 13.8kV, 3000A, 40kA RATED INDDOOR, METAL CLAD SWITCHGEAR, integrated to PSA. • Fifty (50) 10”wellhead piping, sand traps and flow lines (cement lined portion is 10”) from wellhead to the headers.• Eight (8) 24”x16”x12”x10” (telescoping) headers.• Process automation and communication systems for safe monitoring and control from Zuluf Central Processing Facility (ZCPF).• Eight (8) 24” laterals from the headers to the manifolds with scraper launchers and receiver facilities• Two (2) 48”x36”x24” (telescoping) manifolds connecting to the trunk line (with provisions for future connections)• One (1) 42” trunkline connecting the manifolds to the WTP , total length 58 KM , with two (2) Main line valve stations.• Operation, maintenance and security buildings at the manifold area. Show less Project : MANIFA FLANK II & III PROJECT TO REPLACE FLOW LINES, HEADERS & LATERALS (DS-37, DS-41, DS-43 & TNAJIB GATHERING MANIFOLD)The work is to replace existing piping, Instrument, flowmeters and valves of 6 water injection wells flow lines (8" size) , 3 Headers (16"&12") , 3 Lateral lines (12" & 10") & 1 Interface/Gathering manifold 30" in Manifa field. To be replaced with:* 6 flowlines (8") CS internally FBE coated / RTP pipes for under ground section with all instrument and valves.*150 meter of 16" Header CS internally HDPE lined*300 meter of 12" Header CS internally HDPE lined*600 meter of 12" Lateral line CS internally HDPE lined *1800 meter of 10" Lateral line CS internally HDPE lined*150 meter of 30" / 20" Header of interface manifoldWork include installation and configuration of LEL / H2S gas detectors system with horn and beacon lights, upgrade and modification of 3 existing RTUs to accommodate the new signals by adding additional IO cards and relays. SCADA configuration of new IOs. Show less
Construction Manager
Dec 2022 - nowSenior Project Engineer / Acting Project Manager
Jun 2021 - Dec 2022
Licenses & Certifications

Membership engineer
Saudi council of engineersJul 2012- View certificate

Project management professional (pmp)
Project management instituteJan 2024 - View certificate

Membership
IsaJun 2015
Honors & Awards
- Awarded to Mohamed Merghani, PMP®Certificate of Appreciation SADARA Chemical Company Oct 2014
Languages
- arArabic
- enEnglish
Recommendations

Shareena brown
Aspiring Project Manager | 17+ Years in Customer Service Leadership | Expertise in Cross-Functional ...Homewood, Illinois, United States
Germano mugambi
Power System EngineerCopenhagen, Capital Region of Denmark, Denmark
Adam tamás
Marketing & Web Content Coordinator | Sports enthusiastStúrovo, Nitra Region, Slovakia
Sanjula jayawardana
Software Engineer at IFSColombo District, Western Province, Sri Lanka
Luis garcia
Operation Manager at AmazonClarksville, Arkansas, United States
Nadia noriega
Mobile App Designer & DeveloperPanama
Jami singletary
Site Procurement Coordinator at Becton DickinsonRaleigh-Durham-Chapel Hill Area
Sumer sayyed
Technical process specialists| MIS/WFM AnalysisPune, Maharashtra, India
Priscila macacari
Psicóloga Clínica e Social e Docente de Psicologia OrganizacionalJaú, São Paulo, Brazil
Fabi soares / conectabiz
Empreendedora e PsicoterapeutaViamão, Rio Grande do Sul, Brazil
...