
Hyunkyu Woo

Connect with Hyunkyu Woo to Send Message
Connect
Connect with Hyunkyu Woo to Send Message
ConnectTimeline
About me
Senior Team Manager, Hydrogen Distribution Center, HQ, KOGAS, Re-public of Korea
Education

고려대학교
1997 - 1999공학 석사 금속공학Master Degree in Metallurgy Engineering of the nuclear engineering

아주대학교
1990 - 1997Bachelor of Science (BSc) 재료공학
Experience

Korea Gas Corporation
Jul 1999 - Jul 2010Samcheok LNG receiving terminal is planned to be built in the east coast of South Korea. This terminal is designed to store LNG in 12 onshore tanks(200,000m3 per tank) and send out the natu-ral gas having capacity of 780ton/hr. In principle the sea water is necessary for the operation of LNG Plant. It is supplied to the Sea water Open Rack Vaporizer and is necessary for Fire Fighting system at emergency. So to design the intake system and the water treatment system is very im-portant for the KOGAS terminal. Had the following duties Coordination with the contributor (KOGAS,KOGAS R&D,KOGAS-Tech, Daewoo Engineering) assigned to the project of Samcheok LNG Terminal to harmonize the design philosophy Reviewing Basic Design and Plot Plan Developing PFDs and P&IDs Determining LNG pump head (Hydraulic calculation review)- 1st Primary LNG Pump- 2nd Primary LNG Pump Basic Design and Developing the Sea Water system- Seawater Supply facilities for Vaporization ( 12,000m3/hr X 7 units, 6,000m3/hr X 1 unit)- Seawater Supply facilities for Fire Fighting Facility (3,500m3/hr X 3 units )- Sea Water Treatment System(Filtering and Chlorination)- Sea Water Transferring Pipeline(GRP) Estimation of CAPEX Evaluation of the construction material Equipment sizing Completing the detailed engineering Reviewing and developing LNG tank design Reviewing and developing the equipment design(Pressure vessel, Seawater intake system, LNG pump and compressor etc. ) Verifying the 3D simulation of the detail drawing Show less Incheon LNG receiving terminal is the biggest LNG receiving terminal in the world. It has been con-structed according to the plan of 1st and 2nd expansion to meet the rapid increase of natural gas demand of the cosmopolitan area. This terminal has the 20 storage tanks(total 288,000 m3) and 3 send-out trains(total 4740 ton/hr). The additional facilities, including two LNG tanks(200,000m3 per tank) and subsidiary facilities (Capacity 720ton/hr). Had the following duties Coordination of the discipline contributor (Communication, Procurement, Engineering, Sched-ule managing) for 2nd-4th Expansion Reviewing and Approving the detail design of Inground LNG tank(Membrane type, 200,000 m3) Making the estimate of the cost for the construction Reviewing and Approving the capability study for the main equipments Reviewing and Approving the pre-commissioning and commissioning procedure for LNG tank Reviewing and Approving the pre-commissioning and commissioning procedure for Pipe lines and equipments Procurement of the main equipments- Make an estimate, Complete TBE, Review Vendor prints, Managing the progress of delivery Analyzing the cost of construction Permitting on the completion of the construction Developing conceptual studiesAlso including the following activities: Analyzing the fluid dynamics of Pipe lines Developing the tank design Investigating the analytical study of LNG behaviorThese activities were carried out in the following projects: #219,220 LNG Tanks(Membrane type, 200,000m3 per tank) The Main Piping Installation Construction of #219,220 Tank Area Vaporizing and Sending System Erection(540 ton/hr) Vaporizing and Sending System Erection(120 ton/hr) High Pressure Gas Compressor System Erection(20 ton/hr) Sea Water Underground Piping Erection for #219,220 Tank Area Sea Water Underground Piping Erection for 2nd 4th Phase Area DME(Dimethyl ether) Actual Proofing Facility Show less Kogas Seoul Branch Office is managing the supply of natural city gas for the cosmopolitan area. The facilities are largely composed of the main control center, the local governing stations and pipe line network. The main pressure sent by LNG terminal is approximately 5.0~7.0Mpa. It must be decreased according to the pressure for the consumers. Each governing station is composed of the filters, Gas Heaters, Pressure System, Metering and Gas Chro Units including the subsidiary ones. Had the following duties Managing the local governing station Maintenance of the equipments- Filters, Gas Heaters, Pressure System, Metering and Gas-Chro Units Operation of the flow control system Show less Mechanical Engineer, Incheon LNG Terminal in KOGAS, South KoreaAssistant Construction ManagerThe Incheon LNG receiving terminal 2nd Expansion Project, is located in the west coast of South Korea and in charge of supply of natural gas to the metropolitan area. To meet the rapid increase of natural gas demand of this area, the 2nd expansion is ongoing. Had the following duties Managing the whole construction schedule Perform the Quality Control Procurement of the materials Supervise the construction procedure Pipe Erection for Cryogenic service Cold / Hot Insulation Steel Structure Erection Equipment Erection(Vaporizer, Pump, Compressor, Pressure Vessel, Unloading arm) Utility Piping Erection(Above and Underground) Inspect the welding procedure Pre-Commissioning & Commissioning Plan and Procedure Plant Gas-In and Start-Up Procedures Review and approve the inspection reports Monitor the Monthly payment of the construction cost Reporting and Coordination between relative parties Vendor Communication Communication between Contractor and Technical Service ProviderThese activities were carried out in the following projects: #215,216 LNG Tanks(Membrane type, 200,000m3 per tank) The Main Piping Installation Construction of #215,216 Tank Area The Main Piping Installation Construction of #209,210 Tank Area The 2nd Jetty and Trestle Piping and Facilities Erection Construction LNG Unloading Arm Erection Construction(11,000m3/hr) Vaporizing and Sending System Erection(360 ton/hr) Supporting Facilities Construction for the Pilot LNG Tank The Equipments Erection for the Electrical Maintenance Building High-pressure LNG pump (120 T/HR X 80Kg/Cm2 X 22 units) High-pressure seawater-type evaporator (180 T/HR X 77Kg/Cm2) High-pressure combustion-type evaporator (120 T/HR X 77 kG/Cm2) Reciprocation-type high-pressure gas compressor Show less
Mechanical Engineer/Manager
Oct 2008 - Jul 2010Assistant Project Manager
Feb 2007 - Sept 2008Assistant Manager
Aug 2004 - Jan 2007Assistant Manager
Jul 2006 - Sept 2006Manager of Mechanical discipline
Jul 1999 - Aug 2004

Eni
Aug 2010 - Feb 2011Mechanical EngineerZubair Field is located in the Southern area of Iraq, 20 km from Basrah city. The structure of the field is a relatively gentle anticline oriented NNW - SSE, approxi-mately 60 km long and 10-15 km wide. The development plan covers further devel-opment of the Mishrif carbonate reservoir (reference depth 2316.4 m TVDss), the Zubair sandstone, constituted by 3 reservoirs: Upper Shale (reference depth 3170 m TVDss), 3rd pay or Upper Sandstone ( at a reference depth of 3261.4 m TVDss) and the Lower Sandstone or 4th pay reservoir ( at a reference depth of 3459.5 m TVDss). The Zubair Field comprises four domes named respectively (from N to S) Al Ham-mar, Shuaiba, Rafadiyah, and Safwan.The Zubair field has been in operation since 1951 and as such, there is significant existing infrastructure in the field including more than 180 total drilled wells and sur-face processing facilities.Geological, reservoir, and engineering studies were performed using the data availa-ble in the data package and collected so far at site. These studies form the basis for the conceptual study.Effective exploitation of the reservoirs requires pressure support by water injection,dispersed, in Mishrif carbonate reservoir, and peripheral, in Zubair Sandstone reser-voir. During February 2010 the Initial Production Rate (IPR) of Zubair Field was determined in accordance with the methodology and the equipment agreed upon by the parties. The IPR was calculated at 182,778 BOPD with the effective date designated as 18 February 2010. Had the following duties Execute FEED for Oil Degassing Station(DGS) in Mechanical Design (SAIPEM)- Stationary (Desalter, Dehydrator, Boot, Tank etc.)- Rotating (Pump, Compressor etc.)- HAZOP Execute FEED for CPF(Central Production Facility) for Associated Gas Treatment(SAIPEM)- Inlet Facility, Dehydration Unit, Refrigerant System(DPCU), Export Facilities- HAZOP Show less

KOGAS AKKAS B.V.
Mar 2011 - Dec 2015KOGAS has entered into agreement with the Iraqi government to develop the Akkas Field in ac-cordance with the provision of their Gas Development and Production Service Contract (GDPSC).But since the mid of 2014, some risk problem caused the delay of this project. IS, called as Is-lamic state, attacked and occupied the main area of the project. Therefore the project has been suspended and controlled according to the risk management plan so on. At the same time, the exploration for an alternative project instead of the Akkas project had started. Several candidates were examined through the survey of the oil & gas field of the southern Iraqi area. Then new business models and proposals had been prepared and submitted to Iraqi authorities for the ne-gotiation.Had the following duties Analyze the potential risks and the project execution plan - Monitoring and controlling the procured equipment - Establishing the material & equipment procurement strategy - Set up the rescheduling plan of the project Explore alternative project - Execute feasibility study for alternative project - Make an estimate of alternative project Show less KOGAS has entered into agreement with the Iraqi government to develop the Akkas Field in ac-cordance with the provision of their Gas Development and Production Service Contract (GDPSC). The GDPSC states that the PDP was to include, but not be limited to, the following: + FCP(2015) - A programme to achieve First Commercial Production (FCP) at a net dry gas pro-duction rate equal to 25% of the Plateau Production Target (PPT), as soon as possible, but no later than 3 years from approval of the PDP. + PPT(2017) - A programme for construction of processing plant and related facilities and installations within the Akkas Contract Area, to achieve a target rate of 400 MMSCFD, for a period of 13 years, including the extraction of Natural Gas Liquids (NGLs), no later than 6 years from the date upon which the GDPSC becomes effective. Had the following duties Execute Preliminary Development Plan for Feasibility Study - Schlumberger and AMEC Execute FEED for Process and Mechanical Design - Gas Processing Facility and Gathering System, Export Pipeline Including Inlet facility, Dehydration Unit, Refrigerant System, LPG and Condensate Frac-tionation Unit, Gas Compressing Unit, Storage Sphere, Utility Supply etc. Detail Design/Engineering for Gas Processing Facility and Gathering System - Mechanical(Rotating) / Fire Fighting / HVAC / Water Treatment - Material Selection Study - Verifying the 3D simulation of the detail drawing - HAZOP/SIL - HAZID/ENVID Project Management - ITB Preparation, Bidding Evaluation and Scoring, Project Schedule Control - Estimation of CAPEX - Using QUE$TOR (IHS) Show less
Lead Mechanical Engineer
Aug 2014 - Dec 2015Mechanical & Process Engineer/Manager
Mar 2011 - Jul 2014

KOGAS Iraq B.V
Jan 2016 - Feb 2017Lead Mechanical / Process Engineer/ManagerKOGAS has entered into agreement with the Iraqi government to develop the Akkas Field in ac-cordance with the provision of their Gas Development and Production Service Contract (GDPSC).But since the mid of 2014, some risk problem caused the delay of this project. IS, called as Is-lamic state, attacked and occupied the main area of the project. Therefore the project has been suspended and controlled according to the risk management plan so on. At the same time, the exploration for an alternative project instead of the Akkas project had started. Several candi-dates were examined through the survey of the oil & gas field of the southern Iraqi area. Then new business models and proposals had been prepared and submitted to Iraqi authorities for the negotiation. Had the following duties Explore alternative project ①. Tuba ②. Nassiriya_Bin Umar ③. Rafidian_Garaff_Nassiriya ④. West Qurna 2 ⑤. Halfaya ⑥. Middle Furat ⑦. Halfaya_Nassiriya Integrated ⑧. Mansuriya Collect and analyze the material Set up the conceptual process model Perform the conceptual process simulation Make an estimate of alternative project Execute feasibility study for alternative project Negotiate with Iraqi authorities on above proposals Show less

한국가스공사
Mar 2017 - Jan 2020Project Engineer in commissioning team of KOGAS1. Project Name: : Al-Zour LNG Import Project, Contract No. ZOR/EPC-00582. Client: : Kuwait Integrated Petroleum Industries Company (KIPIC)3. PMC: : AMEC Foster Wheeler4. Contractor: : HEC (Leader) + HDEC + KOGAS5. Project Period: : 57 Months (15 May 2016 ~ 12 February 2021)6. Contract Amount: : circa 3 Bil USD7. Milestones: : Stage 1 Commissioning : 10 Sep. 2020 (52M) Provisional Acceptance of Facility : 12 Feb. 2021 (57M)8. Scope of Work:Dredging Works (13.4 Mil. M3)Land Reclamation (8.9 Mil. M3)Seawater Intake (1.4km X 4Lines, I.D 2500 & 3000)Water Outfall (0.3km X 4Lines, I.D 2600)Jetty (#47, #48) & TrestleLNG Storage Tanks : 225,500 m3 x 8 eaRegasification Plant : 3,000 BBTU/day Show less
차장
Mar 2019 - Jan 2020Manager
Dec 2017 - Feb 2019Manager
Mar 2017 - Nov 2017
.webp)
Korea Gas Corporation(KOGAS)
Feb 2020 - nowSenior Manager, Gas to Power Business Developing Team, HQ, KOGAS, Re-public of KoreaI am in charge of developing the overseas Gas to power business including searching and developing, investing. Especially now I am focusing my attention to Asian GtP markets. Any idea and proposal will be welcomed.Has the following duties;①. Search and develop New Oversea Gas to Power Project ②. Prepare Preliminary Project Information Memorandum③. Feasibility Study Report④. Whole Engineering Works Management (Concept Design, FEED)⑤. EPC Management (ITB, Bidding, Contract)⑥. Management of Project Financing⑦. Risk Managements Show less
Senior Team Manager
Jan 2024 - nowSenior Manager
Feb 2020 - Dec 2023
Licenses & Certifications
- View certificate

Gas Engineer Certificate
Human Resources Development Service of Korea 
Aspen HYSYS: Process Modeling
Aspen TechnologyMay 2019
Volunteer Experience
Coordinator
Issued by Korea Gas Corporation on Dec 2005
Associated with Hyunkyu Woo
Languages
- enEnglish
- koKorean
Recommendations

Lucy hay
MPH Recipient from the University of Virginia School of MedicineCharlottesville, Virginia, United States
Alex ryaboy
FSR II at STERIS CorporationBrooklyn, New York, United States
Patrizia reidl
Communication Manager @ Digital Media & Communications WKÖVienna, Vienna, Austria
Brandon relf
Project Manager - PMP, MBABradenton, Florida, United States
Guillermo andres
Operations Manager at Topaz PhilippinesCentral Luzon, Philippines
Omar alahmed
Development Manager | People Leader | Drupal Consultant | ITIL® | PMP® | PMI-ACP® | ZCE® | OCP®Amman, Jordan
Praveen ramesh
Machine Learning Engineer at CVS Health - Building GenAI products | Carnegie Mellon University Alumn...New York, New York, United States
康金山
新浪 - 高级总监Haidian District, Beijing, China
Rohan tuteja
Associate Manager at Pepsico Strategy & Transformation || Summer Intern at Aditya Birla Capital ||NM...New Delhi, Delhi, India
Jessa m.
Sales Support Engineer at The Tri-M GroupOxford, Pennsylvania, United States
Miguel flores
Engineer I at Granite ConstructionSalinas, California, United States
Yurj buzzi
Actor, communication coach & mentor at yuribuzzi.com Creative at Four55 ltd and co-founder of Buzzi ...London, England, United Kingdom
Michael mitchell
Management & Letting Rights IndustryBrisbane, Queensland, Australia
Vivek tajane
Senior Program Manager at Koantek | Co-Founder & Director at CayianPune, Maharashtra, India
Alexandra banks
Market Development RepresentativeFlorence, Alabama, United States
Soujanyo bose
3rd Year @BCREC | Aspiring Frontend Developer | GCP'23Durgapur, West Bengal, India
Maxime gindre
Avionics Business Domain Manager - Thales Italia S.p.A.Vergiate, Lombardy, Italy
Shriram patidar
|| DEHYDRATION ENTHUSIAST || FOOD TECHNOLOGIST || M.TECH. FOOD TECHNOLOGY NIFTEM || B.TECH. AGRICUL...Ujjain, Madhya Pradesh, India
Rutuja bhamare
Technical trainee at fujitsuPune, Maharashtra, India
Mario biancolella
UI Designer | Design System specialistWeilerbach, Rhineland-Palatinate, Germany
...